Working with main contractor Excalon , work can be seen progressing on site with operatives excavating, setting construction formwork, and installing steel reinforcing mesh to enable Heavy Duty Road Crossings to be installed at locations around The Horizon Nuclear Power Wylfa Newydd site.

These road crossings are designed to take loads exceeding 100 tonnes. Other associated work carried out for Excalon included installing around 2,500m of haul road designed for heavy loadings at various points across the site, together with the removal (under an ecological watching brief) of various stone walling and hedgerows .Work is now complete .